House / Elevation
October 5
The driveway and sidewalk are complete
September 29
The siding is installed and the sidewalk is complete.
September 26
The entryway columns have been installed
September 23
Brick is installed and acid washed.
September 11
Brick installation is complete, although the brick has
not been acid washed yet.
September 8
They have started installing the brick.
September 3
The garage door in installed.
September 1
Additional trim has been installed, and the front door sidelights are in. Our brick has been delivered to the site, you can see the three pallets in the yard to the right of the garage.
August 30
All of the windows are installed, and work on the trim has started.
August 24
The roof is completely shingled, and all but the two front lower windows are installed.
August 21
About half of the roof is shingled.
August 19
The roofing underlayment has been started.
August 16
The roof is completely sheathed, and the dormers and porch are complete.
August 15
The roof is about 2/3 sheathed.
August 10
The roof trusses are about 2/3 done.
August 9
The second floor is framed and the first roof trusses are going in.
August 8
The second floor is partially framed
August 4
The second floor deck is complete.
August 3
The first floor walls are framed.
August 2
The first floor exterior walls are in place.
July 24
The front steps are poured, with the forms still in place.
July 19
The foundation has been backfilled.
|