House / Basement

September 14

These photos were taken during our pre-drywall walkthrough.

August 30

Much of the HVAC, plumbing and electrical roughin is complete.

July 27

The basement floor has been poured.

July 24

The vapor barrier is in place (sort of), the steel is set, and the basement is ready for the flat work pour.

July 19

The forms are off the basement walls.